Geomechanical behavior of jointed rock mass versus delay interval in seismic load zone of large-scale blasts

Experimental tests show that velocities of seismic vibrations from quarry blasts generally lower as delay intervals between large-scale blasts are increased. At the same time, a seismically safe delay interval is governed by geological conditions, which vary appreciably within an open pit mine field, and by geotechnical conditions of mining. This study was aimed to obtain theoretical formulas of vibration velocities, compressive stresses and relative strains in rock mass as functions of the delay interval based on the mechanism of seismic waves induced by short-delayed blasting in jointed rock mass. These formulas were to be justified. After review of reference sources, the mechanism of blast-induced seismic waves in jointed rock mass was developed. According to this mechanism, high-velocity collisions of fractured and intact blocks under the action of pressure from detonation products generate elastic waves. The theoretical research allowed formulas for the delay interval dependence of the vibration velocities, compressive stresses and strain rates in rock mass in the seismic impact zone of blasting. The comparison of the mathematical and numerical analysis results with the actual practice data validates the formulas of vibration velocities as function of blast-to-blast delay intervals. These formulas make a framework for the development of regulations for blasting at minimized seismic impact on guarded objects in different geological and geotechnical conditions.

Keywords: large-scale blasts, seismic load, delay interval, blast-induced seismic wave interval, mathematical formulas, vibration velocity, compressive stress, strain rates, justification.
For citation:

Tyupin V. N., Khaustov V. V. Geomechanical behavior of jointed rock mass versus delay interval in seismic load zone of large-scale blasts. MIAB. Mining Inf. Anal. Bull. 2021;(2):45-54. [In Russ]. DOI: 10.25018/0236-1493-2021-2-0-45-54.

Acknowledgements:

The study was supported by the Ministry of Science and Higher Education of the Russian Federation, Grant No. 075-03-2020-474/1 от 05.03.2020.

Issue number: 2
Year: 2021
Page number: 45-54
ISBN: 0236-1493
UDK: 622.2:614.83(075.8)
DOI: 10.25018/0236-1493-2021-2-0-45-54
Article receipt date: 07.05.2020
Date of review receipt: 05.08.2020
Date of the editorial board′s decision on the article′s publishing: 10.01.2021
About authors:

V.N. Tyupin1, Dr. Sci. (Eng.), Professor, e-mail: tyupinvn@mail.ru,
V.V. Khaustov1, Dr. Sci. (Geol. Mineral.),
1 Belgorod State National Research University, 308015, Belgorod, Russia.

 

For contacts:

V.N. Tyupin, e-mail: tyupinvn@mail.ru.

Bibliography:

1. Sadovsky M. A. Seismic of explosions and seismology. Izvestiya AN SSSR. Fizika Zemli. 1987, no 11, pp. 34—42. [In Russ].

2. Adushkin V. V., Spivak A. A. Podzemnye vzryvy [Underground explosions], Moscow, Nauka, 2007, 579 p.

3. Mosinets V. N. Drobyashchee i seysmicheskoe deystvie vzryva v gornykh porodakh [Crushing and seismic action of an explosion in rocks], Moscow, Nedra, 1976, 270 p.

4. Kutuzov B. N. Bezopasnost' vzryvnykh rabot v gornom dele i promyshlennosti: uchebnoe posobie [Safety of blasting in mining and industry. Educational aid], Moscow, Izd-vo «Gornaya kniga», Izd. MGGU, 2009, 670 p.

5. Sovmen V. K., Kutuzov B. N., Mar'yasov A. L., Ekvist B. V., Tokarenko A. V. Seysmicheskaya bezopasnost' pri vzryvnykh rabotakh: Uchebnoe posobie [Seismic safety during blasting. Educational aid], Moscow, Izd-vo «Gornaya kniga», 2002, 228 p.

6. Gospodarikov A. P., Zatsepin M. A. Mathematical modeling of nonlinear boundary value problems of geomechanics. Gornyi Zhurnal. 2019, no 12, pp. 16—20. [In Russ]. DOI: 10.17580/ gzh.2019.12.03.

7. Tseytlin Ya. I., Smoliy N. I. Seysmicheskie i udarnye vozdushnye volny promyshlennykh vzryvov [Seismic and shock air waves of industrial explosions], Moscow, Nedra, 1981, 192 p.

8. Tsibaev S. S., Renev A. A., Pozolotin A. S., Mefodiev S. N. Assessment of seismic impacts on stability of openings in underground mines. MIAB. Mining Inf. Anal. Bull. 2020, no 2, pp. 101–111. [In Russ]. DOI: 10.25018/0236-1493-2020-2-0-101-111.

9. Segarra P., Sanchidrián J. A., Castedo R., López L. M., Del Castillo I. Performance of some coupling methods for blast vibration monitoring. Journal of Applied Geophysics. 2015. Vol. 112. Pp. 129—135.

10. Kumar R., Choudhury D., Bhargava K. Determination of blast-induced ground vibration equations for rocks us-ing mechanical and geological properties. Journal of Rock Mechanics and Geotechnical Engineering. 2016. Vol. 8. No 3. Pp. 341—349. DOI: 10.1016/j.jrmge.2015.10.009.

11. Gui Y. L., Zhao Z. Y., Jayasinghe L. B., Zhou H. Y., Goh A. T. C., Tao M. Blast wave induced spatial variation of ground vibration considering field geological conditions. International Journal of Rock Mechanics and Mining Sciences. 2018. Vol. 101. Pp. 63—68. DOI: 10.1016/j. ijrmms.2017.11.016.

12. Li J. C., Li N. N., Chai S. B., Li H. B. Analytical study of ground motion caused by seismic wave propagation across faulted rock masses. International Journal for Numerical and Analytical Methods in Geomechanics. 2017. Vol. 42. No 1. Pp. 95—109. DOI: 10.1002/nag.2716.

13. Bul'basheva I. A. Upravlenie seysmicheskim vozdeystviem vzryvov na opory LEP pri otkrytoy razrabotke mestorozhdeniy [Management of the seismic effect of explosions on power transmission towers during open pit mining], Candidate’s thesis, Saint-Petersburg, SPbGU, 2019, 19 p.

14. Korshunov G. I., Bulbasheva I. A., Afanasyev P. I. Investigation of seismic effects on power lines during blasting. Occupational Safety in Industry. 2019, no 4, pp. 39—43. [In Russ].

15. Zykov V. S., Ivanov V. V., Sobolev V. V. Investigation of the influence of mass industrial explosions on the stability of underground mines during open-underground mining of coal deposits. Occupational Safety in Industry. 2018, no 11, pp. 19—23. [In Russ].

16. Ignatenko I. M., Yanitsky E. B., Dunaev V.A., Kabelko S. G. Fracturing of the rock mass in the quarry of the Zhelezny mine of Kovdorsky GOK JSC. Gornyi Zhurnal. 2019, no 10, pp. 11—15. [In Russ].

17. Kutuzov B. N., Tyupin V. N. Determination of the sizes of the zones of deformation of a fractured mass by explosion of explosive charge. Izvestiya vysshikh uchebnykh zavedeniy. Gornyy zhurnal. 1983, no 4. С. 53—58. [In Russ].

18. Tyupin V. N. Vzryvnye i geomekhanicheskie protsessy v treshchinovatykh napryazhennykh gornykh massivakh [Explosive and geomechanical processes in fractured stressed mountain ranges], Belgorod, ID «Belgorod» NIU «BelGU», 2017, 192 p.

19. Tkachuk K. M., Tkachev S. I. Investigation of the action of a column charge explosion using high-speed filming. Izvestiya vysshikh uchebnykh zavedeniy. Gornyy zhurnal. 1966, no 4, pp. 73—76. [In Russ].

20. Tyupin V. N. Efficiency of crushing rocks by explosion during preliminary closure of macrocracks. Gornyi Zhurnal. 1978, no 9, pp. 41—44. [In Russ].

Our partners

Подписка на рассылку

Раз в месяц Вы будете получать информацию о новом номере журнала, новых книгах издательства, а также о конференциях, форумах и других профессиональных мероприятиях.